TransactionData centers & digital infrastructure

Powered-shell data center conversion, Reno–Sparks

A non-core REIT warehouse next to a substation and long-haul fiber, with 10 MW of committed power the seller hadn’t priced, converted to a powered shell.

A closed Caldrion transaction. The property, the seller and our partners are not named. Figures are as underwritten at closing; yield on cost, IRR and multiple are targets, not realized results.

At a glance

Size120,000 sq ft
Power10 MW committed utility power, with a path to 30 MW
Acquisition$22.0M
Total capitalization$63.5M
StructureJoint venture, 90/10, with a data center developer

The asset

A 2006 distribution building on 15 acres east of Sparks, next to a utility substation and to long-haul fiber along the I-80 corridor between the Bay Area and Salt Lake City.

The situation

A logistics REIT was selling the building as a non-core warehouse and had not priced in the value of its power capacity.

Why it fit

A secondary market with relatively low-cost power and dense fiber. An existing building with committed power saves years of entitlement and interconnection work.

Business plan

  • Upgrade the building to powered-shell specification for $38.5M: on-site substation and utility interconnection, structural reinforcement of the roof for mechanical equipment, generator and cooling yards, diverse fiber laterals and a secure perimeter.
  • Limit spending beyond $6M of early works until a lease is signed.
  • Sign a 15-year NNN master lease with a colocation operator or hyperscale tenant, with 2.5% annual escalators. The tenant funds its own fit-out (UPS, generators, cooling and IT).

Capital structure

$63.5M total: a construction-to-permanent loan at 60% LTC ($38.1M) plus $25.4M of equity (Caldrion $22.9M, developer $2.5M).

Underwriting at closing

  • 7.75% yield on cost under the lease
  • 6.0% exit cap rate
  • 17.5% target net IRR
  • 2.1x equity multiple
  • Five-year hold, including an 18-month conversion

Key risk

The timing of power delivery and of leasing. Major spending waits for a signed lease, and the utility agreement fixes delivery milestones.

See all our transactions, what we pass on and our criteria.

This case study is provided for information only. It is not an offer of securities or investment advice, and past or targeted results do not indicate future results.